| 700 W | NVIDIA H200 SXM | Maximum configurable TDP for one SXM accelerator; it is not whole-server power. | Jul 2026 | NVIDIA |
| 1,400 W | AMD MI355X OAM | Typical board power for one flagship liquid-cooled-capable accelerator module. | Jul 2026 | AMD |
| 10.2 kW | DGX H100/H200 server | Maximum AC input for an 8U, eight-GPU system—about 1.275 kW per installed GPU including CPUs, memory, fabric, and losses. | current guide | NVIDIA |
| 40.8 kW | 4× DGX H100 rack | Recommended maximum server demand for four air-cooled DGX H100 systems in one rack. | current guide | NVIDIA |
| 72 GPUs | GB200 NVL72 rack | One liquid-cooled rack-scale NVLink domain also carries 36 Grace CPUs. | Jul 2026 | NVIDIA |
| ≈120 kW | GB200 NVL72 rack | Full-load rack power including 18 compute nodes and rack components—not only the 72 GPUs. | Mission Control 2.1 | NVIDIA |
| 7 MW | 10,000 H200 SXM GPUs | Accelerator-only TDP: 10,000 × 700 W. Servers, network, and cooling raise the connection requirement. | derived | NVIDIA input |
| 14 MW | 10,000 MI355X GPUs | Accelerator-only TBP: 10,000 × 1.4 kW; do not quote this as facility load. | derived | AMD input |
| 8.19 MW | 10K H200 facility floor | 7 MW accelerator TDP × Microsoft FY25 PUE 1.17. Still excludes the non-GPU parts already missing from 7 MW. | derived floor | Microsoft PUE |
| 1.56 PUE | industry average | Uptime’s 2024 survey average: 100 MW of IT corresponds to 156 MW total facility power. | 2024, n=526 | Uptime |
| 1.17 PUE | Microsoft fleet | Owned-fleet global average; an efficient hyperscaler reference, not a guarantee for a new site. | FY25 | Microsoft |
| 0.27 L/kWh | Microsoft WUE | Annual cooling and humidification water per IT kWh across Microsoft’s owned fleet. | FY25 | Microsoft |
| ≈171K gal/day | 100 MW IT at WUE 0.27 | 100,000 kW × 24 h × 0.27 L/kWh ÷ 3.785 L/US gal. Site water only; power-plant water is separate. | derived | Microsoft input |
| ≈228K gal/day | 100 MW IT at WUE 0.36 | Same calculation using LBNL’s modeled 2023 U.S. fleet average just over 0.36 L/kWh. | 2023 model | LBNL |
| 18–27°C | server inlet air | ASHRAE recommended dry-bulb envelope for air-cooled A1–A4 equipment; allowable limits are broader by class. | ASHRAE guidance | ASHRAE |
| 100 kW+ | liquid-cooled rack | Density class OCP says hyperscalers were considering; GB200’s ≈120 kW is a shipping example. | 2024 reference | OCP |
| 500 kW+ | near-future AI rack | OCP’s July 2026 infrastructure-standardization callout; a planning horizon, not today’s fleet average. | Jul 2026 | OCP |
| 1 kWh → 1 kWh heat | IT energy conversion | Nearly all server electricity becomes heat in the room; “efficient compute” does not remove the heat-rejection obligation. | physics | LBNL |
| 70–80% | potentially recoverable heat | LBNL’s cited technical potential; usefulness still depends on temperature, distance, and a coincident heat customer. | 2025 review | LBNL |
| 60–80% | AI server operating power | LBNL’s modeled range as a fraction of rated power—evidence against equating nameplate with annual average draw. | 2024 model | LBNL |
| 80% / 40% | training / inference time | LBNL modeled AI server operational time—not measured utilization for every deployment. | 2024 model | LBNL |
| 415 TWh | global data centers | About 1.5% of world electricity consumption in 2024. | 2024 estimate | IEA |
| ≈945 TWh | global data centers | IEA base-case demand in 2030—more than double 2024, but explicitly scenario-dependent. | 2030 forecast | IEA |
| 649 TWh | U.S. data centers | LBNL 2026 reference case for 2030; compounded uncertainty spans 521–843 TWh. | Jun 2026 model | LBNL |
| $9.5–13.3/W | U.S. construction | 2025 traditional data-center build benchmarks: Charlotte to Silicon Valley. Facility construction scope—not land, IT hardware, finance, or energy. | 2025 USD | T&T |
| +7–10% | AI liquid-cooling premium | Turner & Townsend’s U.S. average premium versus equivalent air-cooled capacity. | 2025 analysis | T&T |
| 2–3 years | data center to operation | IEA’s general facility lead-time anchor; transmission, generation, permitting, and equipment can take longer. | 2025 report | IEA |