AI Infrastructure Numbers Everyone Should Know

A neutral, order-of-magnitude reference for sanity-checking an AI facility claim in 60 seconds—from accelerator nameplate power to rack density, PUE, water, construction cost, and grid schedule.

volatile hardware and market figures are dated inline

The numbers

These are comparison anchors, not universal constants. “Derived” rows show transparent arithmetic from cited inputs; vendor power is nameplate unless the row says otherwise.

W / kW / MW = instantaneous powerkWh / TWh = energy over timeIT = compute equipment onlyfacility = IT plus overhead
infra-numbers.tsv — 27 rows
NumberUnit / objectWhat it meansScopePrimary source
700 WNVIDIA H200 SXMMaximum configurable TDP for one SXM accelerator; it is not whole-server power.Jul 2026NVIDIA
1,400 WAMD MI355X OAMTypical board power for one flagship liquid-cooled-capable accelerator module.Jul 2026AMD
10.2 kWDGX H100/H200 serverMaximum AC input for an 8U, eight-GPU system—about 1.275 kW per installed GPU including CPUs, memory, fabric, and losses.current guideNVIDIA
40.8 kW4× DGX H100 rackRecommended maximum server demand for four air-cooled DGX H100 systems in one rack.current guideNVIDIA
72 GPUsGB200 NVL72 rackOne liquid-cooled rack-scale NVLink domain also carries 36 Grace CPUs.Jul 2026NVIDIA
≈120 kWGB200 NVL72 rackFull-load rack power including 18 compute nodes and rack components—not only the 72 GPUs.Mission Control 2.1NVIDIA
7 MW10,000 H200 SXM GPUsAccelerator-only TDP: 10,000 × 700 W. Servers, network, and cooling raise the connection requirement.derivedNVIDIA input
14 MW10,000 MI355X GPUsAccelerator-only TBP: 10,000 × 1.4 kW; do not quote this as facility load.derivedAMD input
8.19 MW10K H200 facility floor7 MW accelerator TDP × Microsoft FY25 PUE 1.17. Still excludes the non-GPU parts already missing from 7 MW.derived floorMicrosoft PUE
1.56 PUEindustry averageUptime’s 2024 survey average: 100 MW of IT corresponds to 156 MW total facility power.2024, n=526Uptime
1.17 PUEMicrosoft fleetOwned-fleet global average; an efficient hyperscaler reference, not a guarantee for a new site.FY25Microsoft
0.27 L/kWhMicrosoft WUEAnnual cooling and humidification water per IT kWh across Microsoft’s owned fleet.FY25Microsoft
≈171K gal/day100 MW IT at WUE 0.27100,000 kW × 24 h × 0.27 L/kWh ÷ 3.785 L/US gal. Site water only; power-plant water is separate.derivedMicrosoft input
≈228K gal/day100 MW IT at WUE 0.36Same calculation using LBNL’s modeled 2023 U.S. fleet average just over 0.36 L/kWh.2023 modelLBNL
18–27°Cserver inlet airASHRAE recommended dry-bulb envelope for air-cooled A1–A4 equipment; allowable limits are broader by class.ASHRAE guidanceASHRAE
100 kW+liquid-cooled rackDensity class OCP says hyperscalers were considering; GB200’s ≈120 kW is a shipping example.2024 referenceOCP
500 kW+near-future AI rackOCP’s July 2026 infrastructure-standardization callout; a planning horizon, not today’s fleet average.Jul 2026OCP
1 kWh → 1 kWh heatIT energy conversionNearly all server electricity becomes heat in the room; “efficient compute” does not remove the heat-rejection obligation.physicsLBNL
70–80%potentially recoverable heatLBNL’s cited technical potential; usefulness still depends on temperature, distance, and a coincident heat customer.2025 reviewLBNL
60–80%AI server operating powerLBNL’s modeled range as a fraction of rated power—evidence against equating nameplate with annual average draw.2024 modelLBNL
80% / 40%training / inference timeLBNL modeled AI server operational time—not measured utilization for every deployment.2024 modelLBNL
415 TWhglobal data centersAbout 1.5% of world electricity consumption in 2024.2024 estimateIEA
≈945 TWhglobal data centersIEA base-case demand in 2030—more than double 2024, but explicitly scenario-dependent.2030 forecastIEA
649 TWhU.S. data centersLBNL 2026 reference case for 2030; compounded uncertainty spans 521–843 TWh.Jun 2026 modelLBNL
$9.5–13.3/WU.S. construction2025 traditional data-center build benchmarks: Charlotte to Silicon Valley. Facility construction scope—not land, IT hardware, finance, or energy.2025 USDT&T
+7–10%AI liquid-cooling premiumTurner & Townsend’s U.S. average premium versus equivalent air-cooled capacity.2025 analysisT&T
2–3 yearsdata center to operationIEA’s general facility lead-time anchor; transmission, generation, permitting, and equipment can take longer.2025 reportIEA
READ THIS FIRST: power is a rate; energy is power × time. PUE and WUE require annual boundary-consistent measurements. A 120 kW rack is not a 120 kW utility request, and a 700 W GPU is not a 700 W server.

Sanity-check console

Enter a cluster assumption. The output makes the accounting boundary explicit; it does not size redundancy, storage, networking, switchgear, or phasing.

cluster-envelope.sh
Accelerator IT7.00 MW
Facility floor8.19 MW
Heat at IT23.88 MMBtu/h
Site water / day499K gal
Facility capex floor$93.4M
Facility floor = accelerator TDP × PUE. This is deliberately a floor because CPU, memory, network, and storage power are absent from accelerator TDP.

Metric glossary

MetricPrecise meaningConcrete exampleGotcha
PUETotal annual facility energy ÷ annual IT equipment energy. Ideal is 1.0.156 MWh ÷ 100 MWh = 1.56It does not measure useful compute, water, carbon, or embodied energy; climate and boundary choices matter.
WUEAnnual site water for cooling/humidification ÷ annual IT energy, in L/kWh.27,000 L ÷ 100,000 kWh = 0.27 L/kWhOn-site WUE excludes water consumed to generate electricity unless separately reported as source WUE.
EREEnergy Reuse Effectiveness credits energy reused outside the data center against total facility energy.(156 − 30) MWh ÷ 100 MWh = 1.26A heat-recovery nameplate is not reused energy; count metered delivery to a real sink.
CUEAnnual operational carbon emissions ÷ annual IT energy, usually kg CO₂e/kWh IT.40,000 kg ÷ 100,000 kWh = 0.40 kg/kWhState whether emissions are location- or market-based and whether Scope 3 is excluded.
Rack densityMaximum or measured IT power in one rack, expressed in kW/rack.4 × 10.2 kW DGX = 40.8 kW/rackAn “average 30 kW rack” says nothing about a 120 kW hot spot the cooling loop must survive.
IT loadPower delivered to compute, storage, and network equipment at the defined measurement point.100 MW IT × PUE 1.17 = 117 MW facilityVendor GPU TDP is not IT load; it omits the rest of the server and network.
Critical loadProtected load the electrical design must sustain through the agreed redundancy path.80 MW critical at N+1 needs spare path capacityIt is a design/resilience boundary, not automatically the same as average IT draw.
NameplateRated maximum or design limit used for safe electrical and thermal provisioning.10.2 kW max DGX ≠ 10.2 kW annual averageUsing nameplate as measured demand overstates energy; using average demand to size breakers is unsafe.

Power scale ladder

The bar uses a logarithmic scale so 700 W and 1 GW fit in one frame. Cost envelopes apply the 2025 U.S. $9.5–13.3/W facility-construction range only where a facility rung makes sense; they exclude IT hardware and land.

Residential analogy uses EIA’s 2022 average purchase of 10,791 kWh/customer/year = 1.232 kW continuous. It compares energy rate, not reliability, coincident peak, transmission, or customer count served.

Power: chip → utility meter

Use boundary math, not GPU multiplication

Start with measured or engineered whole-server power. Add network and storage to reach IT load, then multiply by PUE for facility energy. For a quick upper envelope, four 10.2 kW DGX H100 systems make a 40.8 kW server rack; at PUE 1.17, that rack’s allocated facility burden is 47.7 kW before shared-load nuances.

facility power = (servers + network + storage) × PUE

Nameplate, demand, and energy answer different questions

Nameplate sizes safe circuits. Coincident peak demand sizes the service and capacity contract. Annual energy determines much of the bill and footprint. LBNL’s 2024 model used 60–80% of rated power for operating AI servers and 80% / 40% operational time for training / inference.

For 10.2 kW nameplate, 70% operating power × 80% operational time gives a 5.71 kW annual-average model—not permission to provision only 5.71 kW.

100 MW IT at PUE 1.56 = 156 MW facility. The 56 MW difference is cooling, power conversion, lighting, and other facility overhead. At PUE 1.17, the same IT load is 117 MW: PUE changes the overhead, never the 100 MW of compute.

Cooling: density changes the architecture

Air: optimize before replacing

Contain hot and cold aisles, seal bypass paths, manage blanking panels, and hold server inlets in the vendor/ASHRAE envelope. NVIDIA’s four-DGX rack is 40.8 kW and explicitly caps the reference pattern at four systems for thermodynamic reasons.

Use when: the equipment and rack density remain inside a validated airflow design. Do not use: a fleet-average kW/rack to excuse a hotter local rack.

Direct-to-chip: heat leaves in liquid

Cold plates take high-flux heat from CPUs/GPUs to a coolant distribution unit; residual DIMM, PSU, and network heat may still need air. AMD specifies 2.1 L/min per MI355X OAM and coolant inlet up to 43°C for its eight-GPU platform.

Use when: rack power and chip heat flux outrun economical air delivery. Do not assume: “liquid cooled” means zero facility water consumption.

Immersion / rear-door: different tradeoffs

Immersion places electronics in dielectric fluid; rear-door heat exchangers intercept exhaust at the rack. Both change service procedures, materials compatibility, leakage risk, floor load, and the facility loop.

Decision: compare total solution density—including CDUs and service clearance—not the bare tank or rack number.

Cooling claimSanity checkDecision implication
“Air handles it”Show inlet temperature, airflow, pressure, containment, fan power, and the worst rack—not only average density.40.8 kW is a published air-cooled rack design; ≈120 kW GB200 ships liquid cooled. There is no universal cutoff.
“Warm water is free cooling”Show facility-water supply/return temperatures and outdoor design conditions.Warmer loops can expand economizer hours and heat reuse, but a CDU/pump still consumes power.
“Liquid cooling saves water”Separate closed-loop coolant volume from cooling-tower evaporation and source-water use.A closed chip loop can reject heat through a wet tower or a dry cooler; WUE reveals the site result.
“We can reuse the heat”Name the customer, distance, required temperature, seasonal load, and metered MWh delivered.LBNL cites 70–80% recoverable potential; low-grade heat without a sink has zero reuse value.

Water: state the numerator and boundary

Site WUE is simple; interpretation is not

Microsoft defines WUE as annual liters used for cooling and humidification divided by annual IT kWh. Its FY25 owned-fleet values range from 0.03 L/kWh in EMEA to 0.34 in the Americas, with 0.27 global. Climate, cooling design, and load make a single global comparison hazardous.

100 MW IT × 24 h × 0.27 L/kWh = 648,000 L/day = 171,202 US gal/day

Direct and indirect water are different

Site WUE excludes water consumed by the electricity supply. LBNL models both because thermoelectric generation and hydropower can add a location-dependent indirect footprint. “Zero water for cooling” can be accurate at the facility and incomplete for the workload.

Decision: report site withdrawal, site consumption, and source-energy water separately; do not add unlike boundaries.

Dry is not automatically efficient. Microsoft’s zero-water evaporation design avoids more than 125 million liters per facility per year against its stated FY24 baseline, but the company also says energy use rises nominally. Optimize power and water together, in the actual climate.

Cost and time: capacity is a supply chain

Facility capex is not total cluster cost

Turner & Townsend’s 2025 traditional build benchmarks span $9.5/W in Charlotte to $13.3/W in Silicon Valley. A 100 MW facility therefore implies about $950M–$1.33B in comparable construction scope; high-density liquid cooling adds a reported 7–10% U.S. premium.

Excluded: land, utility off-site work, finance, owner costs outside methodology, and the accelerators/servers themselves. A vendor quote that combines these categories cannot be compared directly.

“Power-on” has multiple clocks

IEA says a data center can be operational in two to three years, while the broader energy system needs longer. ERCOT’s 2026 process studies ≥75 MW large loads in batches and was tracking 438 GW of requests; that queue is requests, not forecast realized demand.

PJM says its reformed generation queue targets one-to-two-year agreements, but large-load service also depends on utility studies, substations, transmission, transformers, permits, and construction. Do not substitute a generation-queue statistic for a load energization promise.

GateEvidence to requestCommon schedule failure
Site + permitsControlled parcel, zoning path, environmental/water permits, construction permit milestones.“Shovel-ready” means marketing-ready, not permit-complete.
Utility serviceSigned study/service agreements, MW by year, firm vs interruptible terms, required upgrades.Treating an application or queue position as reserved capacity.
Long-lead equipmentPurchase orders and delivery dates for transformers, switchgear, generators, chillers/CDUs.Building shell finishes before the power train arrives.
CommissioningIntegrated systems test, load-bank plan, staged rack acceptance, operational runbooks.Calling utility energization “production ready.”
Compute deliveryAllocation, network fabric, storage, spares, firmware/software validation.Power exists while usable accelerator capacity does not.

Edge and advanced checks

Behind-the-meter generation: MW is not enough

A 100 MW continuous campus consumes 2.4 GWh/day. A 100 MW generator nameplate cannot cover that load if it is intermittent, derated by temperature/altitude, down for maintenance, or constrained by fuel. Specify dependable capacity, ramp, startup, minimum load, storage duration, black-start behavior, emissions permits, and N+1 contingencies.

required generator nameplate ≈ continuous load ÷ capacity factor — before reserves

Grid queues: separate load, generation, and transmission

They are related but different processes. ERCOT’s Batch Zero is for large users ≥75 MW; PJM’s quoted one-to-two-year agreement target is for generation interconnection. Ask the serving utility/ISO for the actual study path, milestones, upgrade scope, and energization conditions for the site.

Training and inference are not interchangeable

Training tends toward long, synchronized runs with high accelerator occupancy and network intensity. Inference can be latency-sensitive, bursty, geographically distributed, and provisioned for peak demand. LBNL’s model uses 80% operational time for training and 40% for inference, but a real fleet must be measured at server, rack, and service boundaries.

Flexible load has operational value—and constraints

Checkpointing, workload migration, power capping, and staged commissioning can lower coincident demand or accelerate partial energization. Quantify how many MW can move, for how long, with what notice, and at what recovery cost. “Interruptible” without a tested workload contract is not firm grid flexibility.

Common mistakes / anti-patterns

  1. GPU TDP = facility demand.
    It omits CPUs, memory, storage, network, power conversion, and cooling.
  2. Nameplate = annual draw.
    Nameplate is for safe provisioning; meter data and operating profiles determine energy.
  3. PUE = compute efficiency.
    PUE can improve while useful work per kWh gets worse.
  4. Cross-climate PUE league tables.
    Weather, redundancy, load, boundary, and water tradeoffs differ.
  5. Average rack density sizes cooling.
    The hottest rack and row drive local delivery and return capacity.
  1. Training = inference.
    Their utilization, latency, redundancy, network, and geographic profiles differ.
  2. Peak vendor spec = delivered performance.
    TDP and peak FLOPS do not reveal sustained workload throughput.
  3. Closed-loop liquid = zero water.
    The facility heat-rejection system and power source determine consumption.
  4. Queue request = committed load.
    Requests can be speculative, duplicated, phased, or unable to secure upgrades.
  5. Cost per MW = all-in cluster cost.
    Confirm whether land, utility work, IT, finance, and owner costs are inside the boundary.

Primary-source register

Use the dated source, not this page’s cached number, when approving a design or investment.